Almost New Years!  I made a bit more progress today.

First I got a layer of that wood preservative on the entire roof.  Then I started working on cleaning off the old tar.  Scraping doesn’t work because it would damage the aluminum. Acetone will get it off but slowly. That tar just laughs at denatured alcohol, which is my preferred solvent.

But heat does wonders. I should probably be using a heat gun, but I used my propane torch really low.  It melts the tar and with a putty knife it comes right off.  Then a little Goof-Off.  So I start with this:
DSCF0336
and wind up with this.
DSCF0340
There are also some rust stains.  A little Naval Jelly and this:

DSCF0343

looks like this:

DSCF0345

It’s the roof, so I’m not going to try to get it better than this.  No need to remove more material.  So I have most of the roof panels cleaned and ready to apply butyl tape.  Most of the roof panels are done, and the rest will go pretty quickly.

It bothers me that the stovepipe fittings just screw to the aluminum skin.  It needs some stiffness to support the butyl tape.  So I added some 2×2’s.  Like this.

DSCF0351

You can see plywood delamination around the stovepipe, but it’s heat- not rot.  That’s the heater pipe, and you’ll notice there’s no insulation. I’ll cut out a bunch of that and put some kind of metal cover from the inside.  Fortunately polyiso is good for 250 degrees F, so with an inch or two of clearance it should be fine.  I’ll put a thermometer in the gap to confirm, but that won’t be for several months.